Category Archives: Cherrybank Theater
Equipment Rack
Between waiting for contractors and telecommuting into work, I managed to get quite a few more things done yesterday. After shifting each component around at least 3 times, I finally settled on an equipment rack configuration I liked. I had … Continue reading
Equipment
Was able to work most of the weekend and got quite a bit accomplished. Friday night I unpacked my receiver and CD changer so that I would have some listening material while working on the rest of the room. I … Continue reading
Shelving
Trying to take advantage of the nice weather, I worked outside most of the night priming the shelves for the media storage area. I had previously routed groves in the side panels and put one coat of primer on each … Continue reading
Acoustic Treatments
As some of you may know, when you shop for lumber, a 1×3 is really not 1″ x 3″, but smaller. So when I needed to find 1″ thick furring strips to match the 1″ thick insulation, I looked all … Continue reading
Shelving
Installed shelf standards and brackets for the center speaker and equipment rack. I plan on re-using the MDF shelves from my old Flexi rack, but need to cut them down and repaint them first. I hope to start painting the … Continue reading
Acoustic Treatments
After a couple days of searching, I managed to find a local supplier of the duct insulation recommended for the wall treatments. The supplier actually had two of the many products that can be used. One product is called Owens … Continue reading
Stage, Riser & Proscenium
The framing for the stage and riser was completed last Thursday, but I didn’t get to the sand until Sunday. With the help of my friend Amish (and a good friend at that), we lugged 72 bags (3600lbs) of play … Continue reading
Paint
With painting moving forward in the rest of the house, the theater room has been completed as well. The color is called federal blue, and will be very dark with all the lights turned off. The stage and riser are … Continue reading
Drywall
With the drywall up and primed, we’re at a stand still for now. Once the framers have returned to build out the stage and riser, the rest is up to me. The theater (and house) are getting really close to … Continue reading
Wiring
While the rest of the house was being buttoned up and prepared for drywall by the contractors, I went in and pre-wired all the low voltage cables for speakers, networking and the projector. I also installed conduit between the projector … Continue reading